Mahinerangi Wind Farm Stage 2 (Puke Kapo Hau)
Mercury NZ · Otago
Stage 2 expansion of the Mahinerangi wind farm west of Dunedin (Stage 1, 36MW, commissioned 2011), gifted the name Puke Kapo Hau. Up to 44 modern turbines (down from an earlier 100-turbine consent). In fast-track consenting — the expert panel issued a draft decision in June 2026 — and still subject to Mercury board approval before construction. Estimated ~$550m (indicative).
C
Breakdown▾
58% · Uncertain
Completion Probability — likelihood this proceeds on roughly its stated timeline.
Each axis is a scoring factor (0–100%)
Key facts
- Region
- Otago
- Sector
- Energy
- Status
- Planning
- Estimated value
- $550m
- Indicative completion
- 2030
- Funding status
- No Source
- Lead organisation
- Mercury NZ
- Election risk
- Low
Election risk assessment
Commercial renewable investment — broadly bipartisan — but still in consenting and not yet board-approved, so timing is uncertain.
Government priority alignment
HIGH — New wind generation supporting the renewable-electricity transition.
Chronology
- 2011Stage 1 (36MW) commissioned
- 2025Fast-track application lodged for the Stage 2 expansion
- 2026Expert panel issues draft decision and conditions; board approval still required